Club Floor Payment Schedule

  • At the time of booking/Allotment : 10%.
  • Within 2 months of allotment : 20%
  • At the time of Excavation and Foundation : 15%
  • At the time of Ground Floor Casting : 5%
  • At the time of First Floor Casting : 5%
  • At the time of Second Floor Casting : 5%
  • At the time of Third Floor Casting : 5%
  • At the time of Fourth Floor Casting : 5%
  • At the time of Fifth Floor Casting : 5%
  • At the time of Flooring and Finishing : 20%
  • Possession : 5%